Geogrid in SRW Construction

Publish by Publié par Sophie Rhéaume on le Dec 8, 2017 11:33:07 PM

Paver Pete demonstrates how to properly install geogrid in a segmental retaining wall installation. 

 

STEP 1:

Level the backfill.

STEP 2:

Install a geogrid.

It is recommended to follow the recommendations of an engineer.

Here are our engineer’s specifications in this situation:

  • Grid on top of the first course of blocks, 8 inches from the base
  • Grid length of 8 ½ feet, measured from the face of the block to the tale of the grid

STEP 3:

Drive a spike or a sod staple in the geogrid to tension it properly.

spike-3.jpg

Cover an opening

 The convex curve of our wall created a wedge-shaped opening.

wedge-1.jpg

We solved this problem by adding another course of grid with 4 inches of aggregate.

 A geogrid should always abut and never overlap.

abutting.jpg

It should also always be installed in a straight direction.

 

NEED MORE INFO? THIS ANIMATION COVERS EVERYTHING YOU NEED TO KNOW!

VIEW ON YOUTUBE

JOIN US AT CONTRACTOR SHOWCASE AS WE DISCUSS HOW GEOGRID CAN HELP YOU IMPROVE YOUR BUSINESS!

REGISTER TODAY

 

 

 

Subjects:Sujets: PAVER PETE, CONSTRUCTION, SRW, TECHO-BLOC, SEGMENTAL RETAINING WALL, TENSION, SPIKE, GEOGRID, ENGINEER, OPENING

Leave A Comment

Subscribe To Our Blog

Most Popular

Post By Topic

See all